[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141236,799,1,"单选题","某网络计划如下图，逻辑关系正确的是（ ）。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","E的紧前工作是BD",true,{"key":16,"text":17,"correct":18},"B","A完成后同时进行CF",false,{"key":20,"text":21,"correct":18},"C","AB均完成后进行E",{"key":23,"text":24,"correct":18},"D","F的紧前工作是DE","本题考查的是双代号网络计划。紧排在本工作之前的工作称为紧前工作。紧排在本工作之后的工作称为紧后工作。与之平行进行的工作称为平行工作。由图可知，E的紧前工作是BD。所以选A。参见教材30。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]