[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141235,799,1,"单选题","某双代号网络图如下图所示，存在的错误是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","出现无箭头连线",false,{"key":16,"text":17,"correct":14},"B","出现无箭头节点连线",{"key":19,"text":20,"correct":14},"C","出现多个起点节点",{"key":22,"text":23,"correct":24},"D","工作代号相同",true,"本题主要考查的是双代号网络计划。工作①→②，用两条箭线表示是错误的，在双代号网络图中每一项工作都必须用一条箭线和两个圆圈中的号码来表示。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]