[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141232,799,1,"单选题","某道路工程在进行基层和面层施工时，为了给面层铺设提供工作面和工作条件，需待基层铺设一定时间后才能进行面层摊铺，这种时间间隔是（）时距。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","STS",true,{"key":16,"text":17,"correct":18},"B","FTF",false,{"key":20,"text":21,"correct":18},"C","STF",{"key":23,"text":24,"correct":18},"D","FTS","本题主要考查对时间间隔的理解。 工作的搭接顺序关系是用前项工作的开始或完成时间与其紧后工作的开始或完成时间之间的间距来表示，具体有四类： 为了给面层铺设提供工作面和工作条件，需待基层铺设开始一定时间后，面层摊铺才能开始进行，因此，这种时间间距是从基层铺设工作开始时间到面层摊铺工作开始时间的时间间距，即STS时距。 综上所述，本题正确答案为A。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]