[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141227":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141227,799,2,"多选题","在各种计划方法中，（ ）的工作进度线与时间坐标相对应。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","形象进度计划",false,{"key":16,"text":17,"correct":18},"B","横道图计划",true,{"key":20,"text":21,"correct":14},"C","单代号搭接网络计划",{"key":23,"text":24,"correct":14},"D","双代号网络计划",{"key":26,"text":27,"correct":18},"E","双代号时标网络计划","BE","本题主要考查进度计划。 工作进度线与时间坐标相对应的计划方法有横道图计划和双代号时标网络计划，形象进度计划、单代号搭接网络计划、双代号网络计划只能反映各工种之间的逻辑关系以及持续的工作时间，没有时间坐标。 综上所述，本题正确选项为BE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]