[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141212":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141212,799,1,"单选题","（2019年真题）关于如下横道图进度计划的说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","如果不要求工程连续，工期可压缩1周",false,{"key":16,"text":17,"correct":14},"B","圈梁浇筑和基础回填间的流水步距是2周",{"key":19,"text":20,"correct":14},"C","所有工作都没有机动时间",{"key":22,"text":23,"correct":24},"D","圈梁浇筑工作的流水节拍是2周",true,"P117-118 A错误,此工期是最短工期,工期不可压缩; B错误,圈梁浇筑和基础回填间的流水步距是4周。 C选项错误，在基础回填工作中,因为受限于基础回填的施工段3 ,所以基础回填的施工段1和施工段2可以左移,因此具有机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]