[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141211":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141211,799,1,"单选题","一般情况下，横道图能反映出工作的（ ）。( 2015真题 )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总时差",false,{"key":16,"text":17,"correct":14},"B","最迟开始时间",{"key":19,"text":20,"correct":21},"C","持续时间",true,{"key":23,"text":24,"correct":14},"D","自由时差","本题考查的是横道图进度计划的编制方法。横道图计划表中的进度线（横道）与时间坐标相对应，表达的是工作的持续时间。参见教材27。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]