[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141210,799,1,"单选题","某工程基础包含开挖基槽、浇筑混凝土垫层，砌筑砖基础三项工作，分三个施工段组织流水施工，每项工作均由一个专业班组施工，各工作在各施工段上的流水节拍分别是4天、1天和2天，混凝土垫层和砖基础之间有1天的技术间歇。在保证各专业班组连续施工的情况下，完成该基础施工的工期是（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":21},"C","18",true,{"key":23,"text":24,"correct":14},"D","22","本题考查的是横道图进度计划的编制方法。利用大差法计算K12=10，K23=1，所以基础工程流水工期为：10+1+2+2+2+1=18天。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]