[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141203":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141203,799,2,"多选题","建设工程项目总进度目标认证时，在进行项目的工作编码前应完成的工作有（ ）。 2016",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","编制各层进度计划",false,{"key":16,"text":17,"correct":14},"B","协调各层进度计划的关系",{"key":19,"text":20,"correct":21},"C","调查研究和收集资料",true,{"key":23,"text":24,"correct":21},"D","进度计划系统的结构分析",{"key":26,"text":27,"correct":21},"E","项目结构分析","CDE","本题考查的是项目总进度目标论证的工作步骤。建设工程项目总进度目标论证的工作步骤如下：（1）调查研究和收集资料；（2）项目结构分析；（3）进度计划系统的结构分析；（4）项目的工作编码；（5）编制各层（各级）进度计划；（6）协调各层进度计划的关系，编制总进度计划；（7）若所编制的总进度计划不符合项目的进度目标，则设法调整；（8）若经过多次调整，进度目标无法实现，则报告项目决策者。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]