[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141201,799,1,"单选题","建设工程项目总进度目标论证的工作包括：①编制各层进度计划；②项目结构分析；③编制总进度计划；④项目的工作编码。其正确的工作程序是（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②→④→①→③",true,{"key":16,"text":17,"correct":18},"B","④→③→②→①",false,{"key":20,"text":21,"correct":18},"C","②→④→③→①",{"key":23,"text":24,"correct":18},"D","④→②→①→③","本题考查的是项目总进度目标论证的工作步骤。（1）调查研究和收集资料；（2）项目结构分析；（3）进度计划系统的结构分析；（4）项目的工作编码；（5）编制各层进度计划；（6）协调各层进度计划的关系，编制总进度计划。（7）若所编制的总进度计划不符合项目的进度目标，则设法调整。（8）若经过多次调整，进度目标无法实现，则报告项目决策者。参见教材19。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]