[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141200":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141200,799,2,"多选题","项目总进度目标认证时应调研和收集的资料包括（）。2018真题",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目决策阶段有关项目进度目标确定的情况和资料",true,{"key":16,"text":17,"correct":14},"B","与进度有关的该项目组织、管理、经济和技术资料",{"key":19,"text":20,"correct":14},"C","类似项目的进度资料",{"key":22,"text":23,"correct":24},"D","该项目施工总承包单位的信用等级",false,{"key":26,"text":27,"correct":14},"E","该项目的总体部署","ABCE","本题考查的是项目总进度目标论证的工作步骤。调查研究和收集资料包括如下工作：（1）了解和收集项目决策阶段有关项目进度目标确定的情况和资料；（2）收集与进度有关的该项目组织、管理、经济和技术资料；（3）收集类似项目的进度资料；（4）了解和调查该项目的总体部署；（5）了解和调查该项目实施的主客观条件等。参见教材19。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]