[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141197":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141197,799,1,"单选题","关于大型建设工程项目结构分析的说法，正确的是（ ）。2014",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目结构分析是将整个项目逐层分解，并确立工作目录",true,{"key":16,"text":17,"correct":18},"B","项目结构分析是将整个项目逐层分解，并确立工作编码",false,{"key":20,"text":21,"correct":18},"C","项目结构分析是将项目计划逐层分解，并确立工作目录",{"key":23,"text":24,"correct":18},"D","项目结构分析是将项目计划逐层分解，并确立工作编码","大型建设工程项目的结构分析是根据编制总进度纲要的需要，将整个项目进行逐层分解，并确立相应的工作目录。参见教材27。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]