[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141196":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141196,799,2,"多选题","建设工程项目总进度目标论证时，调查研究和收集资料工作包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","收集类似项目进度资料",true,{"key":16,"text":17,"correct":14},"B","收集与进度有关的该项组织资料",{"key":19,"text":20,"correct":14},"C","了解该项目的总体部署",{"key":22,"text":23,"correct":14},"D","了解有关前期该项目进度目标的确定资料",{"key":25,"text":26,"correct":27},"E","了解项目的工作编码资料",false,"ABCD","调查研究和收集资料包括如下工作： （1）了解和收集项目决策阶段有关项目进度目标确定的情况和资料； （2）收集与进度有关的该项目组织、管理、经济和技术资料； （3）收集类似项目的进度资料； （4）了解和调查该项目的总体部署； （5）了解和调查该项目实施的主客观条件等。参见教材26。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]