[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141195":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141195,799,2,"多选题","在建设工程项目总进度目标论证过程中，项目的工作编码应考虑对不同的（ ）进行标识。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计划形式",false,{"key":16,"text":17,"correct":18},"B","计划层",true,{"key":20,"text":21,"correct":18},"C","计划对象",{"key":23,"text":24,"correct":14},"D","计划方法",{"key":26,"text":27,"correct":14},"E","资源类别","BC","本题主要考查建设工程项目总进度目标的论证。 项目的工作编码指的是每一个工作项的编码，编码有各种方式，编码时应考虑的因素有：对不同计划层的标识；对不同计划对象的标识；对不同工作的标识。 综上所述，本题正确答案为BC。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]