[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141193,799,1,"单选题","论证大型建设工程项目总进度目标时，项目结构分析是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","根据建立进度计划系统的需要，分析进度计划之间的关系",false,{"key":16,"text":17,"correct":14},"B","根据项目合同体系，分析影响总进度目标实现的合同交界面",{"key":19,"text":20,"correct":14},"C","根据建立进度计划系统的需要，分析确定进度计划的层次",{"key":22,"text":23,"correct":24},"D","根据编制总进度纲要的需要，将整个项目逐层分解并确定相应的工作目录",true,"本题主要考查建设工程项目总进度目标的论证。 大型建设工程项目的结构分析是根据编制总进度纲要的需要，将整个项目进行逐层分解并确立相应的工作目录。 综上所述，本题正确选项是D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]