[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141188,799,1,"单选题","论证建设工程项目总进度目标，需要进行：①总进度计划的编制；②进度计划系统结构分析；③项目结构的分析等多项工作。仅就上述三项工作而言，其正确的顺序为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1-2-3",false,{"key":16,"text":17,"correct":14},"B","2-3-1",{"key":19,"text":20,"correct":14},"C","3-1-2",{"key":22,"text":23,"correct":24},"D","3-2-1",true,"本题考核的是项目总进度目标论证的工作步骤。 工作步骤为： （1）调查研究和收集资料； （2）项目结构分析； （3）进度计划系统的结构分析； （4）项目的工作编码； （5）编制各层进度计划。 综上所述，正确选项为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]