[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141181":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141181,799,1,"单选题","某工程采用建设项目工程总承包的模式，则项目总进度目标的控制是（）的任务。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主方与监理方",false,{"key":16,"text":17,"correct":18},"B","业主方与工程总承包方",true,{"key":20,"text":21,"correct":14},"C","监理方与工程总承包方",{"key":23,"text":24,"correct":14},"D","工程总承包方与设计方","本题考查的是项目总进度目标论证的工作内容。建设工程项目总进度目标的控制是业主方项目管理的任务。若采用建设项目工程总承包的模式，协助业主进行项目总进度目标的控制也是建设项目工程总承包方的项目管理任务。参见教材18。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]