[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141180":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141180,799,1,"单选题","在进行建设工程项目总进度目标控制前，首先应分析和认证（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度目标实现的可能性",true,{"key":16,"text":17,"correct":18},"B","进度计划系统的完整性",false,{"key":20,"text":21,"correct":18},"C","进度计划方法的适用性",{"key":23,"text":24,"correct":18},"D","进度控制方法的合理性","本题考查的是项目总进度目标论证的工作内容。在进行建设工程项目总进度目标控制前，首先应分析和论证进度目标实现的可能性。参见教材24。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]