[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141178":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141178,799,2,"多选题","建设工程项目总进度目标论证的主要任务有（ ）。( 2015真题 )",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","总进度规划编制",true,{"key":16,"text":17,"correct":14},"B","工程实施条件分析",{"key":19,"text":20,"correct":14},"C","工程实施策划",{"key":22,"text":23,"correct":24},"D","项目总进度目标确定",false,{"key":26,"text":27,"correct":24},"E","项目经济评价","ABC","本题考查的是项目总进度目标论证的工作内容。总进度目标论证的主要内容包括总进度规划的编制工作、工程实施的条件分析和工程实施策划方面的问题。参见教材26。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]