[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141177":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141177,799,1,"单选题","关于大型建设工程项目总进度目标论证的说法，正确的是（ ）。(单项选择题) ( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","大型建设工程项目总进度目标论证的核心工作是编制总进度纲要",false,{"key":16,"text":17,"correct":18},"B","大型建设工程项目总进度目标论证首先开展的工作是调查研究和收集资料",true,{"key":20,"text":21,"correct":14},"C","大型建设工程项目总进度目标的确定应在项目的实施阶段进行",{"key":23,"text":24,"correct":14},"D","若编制的总进度计划不符合项目的总进度目标，应调整总进度目标","本题考查的是项目总进度目标论证的工作内容、项目总进度目标论证的工作步骤。选项A错误，正确的表述应为“大型建设工程项目总进度目标论证的核心工作是通过编制总进度纲要论证总进度目标实现的可能性”。选项C错误，正确的表述应为“建设工程项目总进度目标，应在项目决策阶段项目定义时确定”。选项D错误，正确的表述应为“若编制的总进度计划不符合项目的总进度目标，则设法调整”。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]