[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141175":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141175,799,2,"多选题","项目总进度纲要主要用于论证总进度目标实现的可能性，其内容包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目实施的总体部署",true,{"key":16,"text":17,"correct":14},"B","里程碑事件的计划进度目标",{"key":19,"text":20,"correct":14},"C","总进度目标实现的条件",{"key":22,"text":23,"correct":24},"D","施工总进度规划",false,{"key":26,"text":27,"correct":24},"E","单项工程和单位工程进度计划","ABC","本题主要考查项目总进度纲要的内容。 项目总进度纲要的主要内容包括：项目实施的总体部署、总进度规划、各子系统进度规划、确定里程碑事件的计划进度目标、总进度目标实现的条件和应采取的措施等。 综上所述，本题正确答案为ABC。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]