[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141173":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141173,799,2,"多选题","在建设工程项目总进度目标论证中，项目的工作编码是指一个工作项的编码，编码时应考虑的因素包括对不同（ ）的标识。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","计划层",true,{"key":16,"text":17,"correct":14},"B","计划对象",{"key":19,"text":20,"correct":14},"C","工作类别",{"key":22,"text":23,"correct":24},"D","计划方式",false,{"key":26,"text":27,"correct":24},"E","计划目标","ABC","本题主要考查项目总进度目标论证中工作编码。 项目的工作编码指的是每一个工作项的编码，编码时应考虑对不同计划层、不同计划对象（如不同子项目）、对不同工作（如设计工作、招标工作和施工工作）的标识等。 综上所述，本题正确答案为ABC项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]