[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141171":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141171,799,2,"多选题","在建设工程项目的实施阶段，项目总进度应包括（ ）等。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设计工作进度",true,{"key":16,"text":17,"correct":14},"B","施工前准备工作进度",{"key":19,"text":20,"correct":14},"C","工程物资采购工作进度",{"key":22,"text":23,"correct":14},"D","项目动用前准备工作进度",{"key":25,"text":26,"correct":27},"E","项目后评价工作进度",false,"ABCD","本题主要考查项目总进度的内容。 ABCD项：在项目的实施阶段，项目总进度包括：设计前准备阶段的工作进度;设计工作进度；招标工作进度；施工前准备工作进度；工程施工和设备安装进度；工程物资采购工作进度；项目动用前的准备工作进度等。故正确。 E项：不属于项目实施阶段的项目总进度，故错误。 综上所述，本题正确答案为ABCD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]