[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141166":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141166,799,1,"单选题","对建设工程项目进度目标进行分析和论证，其目的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","论证进度目标是否合理",true,{"key":16,"text":17,"correct":18},"B","制定进度控制措施",false,{"key":20,"text":21,"correct":18},"C","论证进度目标实现的经济性",{"key":23,"text":24,"correct":18},"D","确定调整进度目标的方法","本题考核的是进度目标的分析和论证。 进度目标分析和论证的目的是论证进度目标是否合理，进度目标有否可能实现，如果经过科学的论证，目标不可能实现，则必须调整目标。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]