[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141164":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141164,799,1,"单选题","为让业主方各工作部门和项目各参与方协同工作，可利用（ ）进行基于互联网的辅助进度控制。2014",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","P3项目管理软件",false,{"key":16,"text":17,"correct":18},"B","项目信息门户",true,{"key":20,"text":21,"correct":14},"C","MS Project",{"key":23,"text":24,"correct":14},"D","MS Visio","本题考查的是辅助进度控制。为使业主方各工作部门和项目各参与方方便快捷地获取进度信息，可利用项目信息门户作为基于互联网的信息处理平台辅助进度控制。参见教材25。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]