[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141160":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141160,799,1,"单选题","（2020年真题）某项目施工横道图进度计划如下表，如果第二层支设模板需要在第一层浇筑混凝土完成1天后才能开始，则有1天的层间技术间歇，正确的层间间隙是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Z1",false,{"key":16,"text":17,"correct":18},"B","Z3",true,{"key":20,"text":21,"correct":14},"C","Z2",{"key":23,"text":24,"correct":14},"D","Z4","P114-115 第二层模板支设在第一层浇筑混凝土完成1天后才能开始，在图中显示的距离为Z3。答案选B",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]