[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141157":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141157,799,1,"单选题","建设项目管理供货进度计划应包括的供货环节是（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采购、制造、运输",true,{"key":16,"text":17,"correct":18},"B","采购、制造、安装",false,{"key":20,"text":21,"correct":18},"C","选型、制造、运输",{"key":23,"text":24,"correct":18},"D","选型、供货、存储","本题考查的是项目进度控制的任务。供货进度计划应包括供货的所有环节，如采购、加工制造、运输等。参见教材16。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]