[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141156":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141156,799,1,"单选题","某建设工程项目按施工总进度计划、各单位工程进度计划及相应分部工程计划组成了计划系统，该计划系统是由多个相互关联的不同（）的进度组成。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","深度",true,{"key":16,"text":17,"correct":18},"B","项目参与方",false,{"key":20,"text":21,"correct":18},"C","功能",{"key":23,"text":24,"correct":18},"D","周期","本题考查的是不同类型的建设工程项目进度计划系统。由不同深度的进度计划构成的计划系统，包括：（1）总进度规划（计划）；（2）项目子系统进度规划（计划）；（3）项目子系统中的单项工程进度计划等。参见教材17。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]