[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141152":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141152,799,2,"多选题","由不同功能的计划构成的进度计划系统包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","总进度规划",false,{"key":16,"text":17,"correct":14},"B","项目子系统进度规划",{"key":19,"text":20,"correct":21},"C","控制性进度计划",true,{"key":23,"text":24,"correct":21},"D","指导性进度计划",{"key":26,"text":27,"correct":14},"E","设计进度计划","CD","本题主要考查进度计划系统的分类。 由不同功能的计划构成的进度计划系统包括：控制性进度计划、、指导性进度计划、实施性进度计划。 综上所述，本题正确答案为CD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]