[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141149":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141149,799,1,"单选题","在建设工程项目进度计划系统中，由业主方、设计方、施工和设备安装方编制的进度计划应与（ ）编制的进度计划相互协调。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理方",false,{"key":16,"text":17,"correct":14},"B","政府行政主管部门",{"key":19,"text":20,"correct":14},"C","投资方",{"key":22,"text":23,"correct":24},"D","采购和供货方",true,"本题考核的是建设工程项目进度计划系统中的内部关系。 在建设工程项目进度计划系统中各进度计划或各子系统进度计划编制和调整时必须注意其相互间的联系和协调，如业主方编制的整个项目实施的进度计划、设计方编制的进度计划、施工和设备安装方编制的进度计划与采购和供货方编制的进度计划之间的联系和协调等。 综上所述，正确选项为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]