[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141147":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141147,799,1,"单选题","下列关于项目进度计划系统的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目进度计划系统应该在项目决策阶段完成",false,{"key":16,"text":17,"correct":14},"B","项目进度计划系统应该在开工之前完成",{"key":19,"text":20,"correct":14},"C","项目进度计划系统应该在施工图招标前完成",{"key":22,"text":23,"correct":24},"D","项目进度计划系统是随着项目的进展逐步形成的",true,"本题主要考查项目进度计划系统的形成。 建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，它是项目进度控制的依据。由于各种进度计划编制所需要的必要资料是在项目进展过程中逐步形成的，因此项目进度计划系统的建立和完善也有一个过程，它是逐步形成的。所以D项正确，ABC项错误。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]