[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141146":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141146,799,1,"单选题","作为建设工程项目进度控制的依据，建设工程项目进度计划系统应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在项目的前期决策阶段建立",false,{"key":16,"text":17,"correct":14},"B","在项目的初步设计阶段完善",{"key":19,"text":20,"correct":21},"C","在项目的进展过程中逐步形成",true,{"key":23,"text":24,"correct":14},"D","在项目的准备阶段建立","本题考核的是建设工程项目进度计划系统。 建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，它是项目进度控制的依据。由于各种进度计划编制所需要的必要资料是在项目进展过程中逐步形成的，因此项目进度计划系统的建立和完善也有一个过程，它是逐步形成的。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]