[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141144":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141144,799,2,"多选题","业主方进度控制的任务是控制整个项目实施阶段的进度，包括控制（ ）以及施工进度。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设计准备阶段的工作进度",true,{"key":16,"text":17,"correct":14},"B","物资采购工作进度",{"key":19,"text":20,"correct":21},"C","征地拆迁工作进度",false,{"key":23,"text":24,"correct":14},"D","项目动用前准备阶段工作进度",{"key":26,"text":27,"correct":14},"E","设计工作进度","ABDE","本题主要考查业主方项目进度控制的任务。 业主方项目进度控制的任务是控制整个项目实施阶段的进度，包括控制设计准备阶段的工作进度、设计工作进度、施工进度、物资采购工作进度、以及项目动用前准备阶段的工作进度。 综上所述，本题正确答案为ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]