[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141143":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141143,799,1,"单选题","施工方进度控制的任务是依据（ ）对施工进度的要求控制施工进度。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理规划",false,{"key":16,"text":17,"correct":18},"B","施工任务委托合同",true,{"key":20,"text":21,"correct":14},"C","施工任务单",{"key":23,"text":24,"correct":14},"D","设计任务书","本题主要考查施工方进度控制的任务。 施工方进度控制的任务是依据施工任务委托合同对施工进度的要求控制施工工作进度，这是施工方履行合同的义务。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]