[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141142":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141142,799,1,"单选题","业主方控制设计进度的依据是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计合同",false,{"key":16,"text":17,"correct":14},"B","设计进度计划",{"key":19,"text":20,"correct":21},"C","出图计划",true,{"key":23,"text":24,"correct":14},"D","设计目标","本题主要考查业主方控制设计进度的依据。 业主方进度控制的任务是控制整个项目实施阶段的进度，包括控制设计准备阶段的工作进度、设计工作进度、施工进度、物资采购工作进度，以及项目动用前准备阶段的工作进度。在国际上，设计进度计划主要是各设计阶段的设计图纸（包括有关的说明）的出图计划，在出图计划中标明每张图纸的名称、图纸规格、负责人和出图日期。出图计划是设计方进度控制的依据，也是业主方控制设计进度的依据。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]