[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141141":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141141,799,1,"单选题","设计方进度控制的任务是依据（ ）对设计工作进度的要求控制设计工作进度，这是设计方履行合同的义务。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可行性研究报告",false,{"key":16,"text":17,"correct":14},"B","设计标准和规范",{"key":19,"text":20,"correct":21},"C","设计任务委托合同",true,{"key":23,"text":24,"correct":14},"D","设计总进度纲要","本题主要考查设计方进度控制的任务。 设计方进度控制的任务是依据设计任务委托合同对设计工作进度的要求控制设计工作进度，这是设计方履行合同的义务。 综上所述，本题正确选项为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]