[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141139,799,1,"单选题","建设项目设计方进度控制的任务是依据（ ）对设计工作进度的要求，控制设计工作进度。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可行性研究报告",false,{"key":16,"text":17,"correct":14},"B","设计大纲",{"key":19,"text":20,"correct":14},"C","设计总进度纲要",{"key":22,"text":23,"correct":24},"D","设计任务委托合同",true,"本题主要考查项目进度控制的任务依据。 设计方进度控制的任务是依据设计任务委托合同对设计工作进度的要求控制设计工作进度，这是设计方履行合同的义务。 综上所述，正确选项为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]