[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141138,799,1,"单选题","业主方项目进度控制的任务是控制（ ）的进度。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目设计阶段",false,{"key":16,"text":17,"correct":14},"B","整个项目决策阶段",{"key":19,"text":20,"correct":14},"C","项目施工阶段",{"key":22,"text":23,"correct":24},"D","整个项目实施阶段",true,"本题主要考查业主方项目进度控制的任务。 业主方项目进度控制的任务是控制整个项目实施阶段的进度，包括控制设计准备阶段的工作进度、设计工作进度、施工进度、物资采购工作进度、以及项目动用前准备阶段的工作进度。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]