[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141137":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141137,799,1,"单选题","施工方应视项目特点和进度控制的需要，编制（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目动用前准备工作计划",false,{"key":16,"text":17,"correct":18},"B","施工进度计划",true,{"key":20,"text":21,"correct":14},"C","设计进度计划",{"key":23,"text":24,"correct":14},"D","主要设备采购工作计划","本题主要考查施工方进度控制。 B项：编制进度计划时，施工方应视项目的特点和施工进度控制的需要，B正确。 AD项：属于业主方计划，故AD项错误。 C项：属于设计方计划。故C项错误。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]