[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141136":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141136,799,1,"单选题","建设工程项目的业主和参与方都有进度控制的任务，各方（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","控制的目标相同、但控制的时间范畴不同",false,{"key":16,"text":17,"correct":14},"B","控制的目标不同、但控制的时间范畴相同",{"key":19,"text":20,"correct":14},"C","控制的目标和时间范畴均相同",{"key":22,"text":23,"correct":24},"D","控制的目标和时间范畴各不相同",true,"本题主要考查业主和参与方进度控制的任务。如下表： 由上表可知，业主和参与方进度控制的任务控制的目标和时间范畴各不相同。 综上所述，本题正确选项为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]