[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141135,799,1,"单选题","在项目实施阶段，设计方编制的设计工作进度应尽可能与招标、施工和（ ）等工作进度相协调。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目选址",false,{"key":16,"text":17,"correct":14},"B","可行性研究",{"key":19,"text":20,"correct":14},"C","竣工验收",{"key":22,"text":23,"correct":24},"D","物资采购",true,"本题主要考查设计方进度控制的任务。 设计方进度控制的任务是依据设计任务委托合同对设计工作进度的要求控制设计工作进度，这是设计方履行合同的义务。另外，设计方应尽可能使设计工作的进度与招标，施工和物资采购等工作进度相协调。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]