[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141133":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141133,799,1,"单选题","建设工程项目在施工时盲目赶工，会导致（ ）。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","安全事故发生的概率减小",false,{"key":16,"text":17,"correct":14},"B","施工成本增加的概率减小",{"key":19,"text":20,"correct":14},"C","文明施工实现的概率增加",{"key":22,"text":23,"correct":24},"D","质量事故发生的概率增加",true,"本题考查的是项目进度控制的目标。不是正常有序地施工，而盲目赶工，难免会导致施工质量问题和施工安全问题的出现，并且会引起施工成本的增加。参见教材22。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]