[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141124":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141124,799,2,"多选题","某项目成本及成本构成比例数据如下表，正确的有（ ）。( 2015真题 )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","成本增加比例最大的是间接成本",true,{"key":16,"text":17,"correct":18},"B","成本降低最多的项目是机械费",false,{"key":20,"text":21,"correct":14},"C","成本节约效益最大的是材料费",{"key":23,"text":24,"correct":14},"D","成本节约做得好的是措施费",{"key":26,"text":27,"correct":14},"E","直接成本增加比例最大的是人工费","ACDE","本题考查的是施工成本分析的方法。成本降低最多的是材料费。参见教材115。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]