[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141120,799,1,"单选题","某施工项目某月的成本数据如下表，应用差额计算法得到预算成本增加对成本的影响是（ ）万元。2014",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","12.0",false,{"key":16,"text":17,"correct":14},"B","8.0",{"key":19,"text":20,"correct":14},"C","6.4",{"key":22,"text":23,"correct":24},"D","1.6",true,"利用差额计算法得：（640-600）×4%=1.6万元。参见教材14～115。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]