[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141119,799,1,"单选题","下列施工成本分析方法中，用来分析各种因素对成本影响程度的是（ ）。2014",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","相关比率法",false,{"key":16,"text":17,"correct":18},"B","连环置换法",true,{"key":20,"text":21,"correct":14},"C","比重分析法",{"key":23,"text":24,"correct":14},"D","动态比率法","本题考查的是施工成本分析的基本方法。因素分析法又称连环置换法，可用来分析各种因素对成本的影响程度。参见教材13。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]