[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141113,799,1,"单选题","某项目施工成本数据如下表，根据差额计算法，成本降低率提高对成本降低额的影响程度为（ ）万元。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.6",false,{"key":16,"text":17,"correct":14},"B","0.7",{"key":19,"text":20,"correct":14},"C","1.1",{"key":22,"text":23,"correct":24},"D","1.2",true,"本题考查的是施工成本分析的基本方法。成本降低率提高对成本降低额的影响为（3.5%-3%）×240=1.2万元。参见教材15。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]