[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141104":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141104,799,2,"多选题","单位工程竣工成本分析包括的内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","目标利润分析",false,{"key":16,"text":17,"correct":14},"B","目标成本分析",{"key":19,"text":20,"correct":14},"C","预算成本分析",{"key":22,"text":23,"correct":24},"D","主要资源节超对比分析",true,{"key":26,"text":27,"correct":24},"E","主要技术节约措施及其经济效果分析","DE","本题主要考查成本分析的内容。 单位工程竣工成本分析应包括以下三方面的内容：竣工成本分析；主要资源节超对比分析；主要技术节约措施及经济效果分析。 综上所述，本题正确答案为DE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]