[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141098":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141098,799,1,"单选题","在进行月（季）度成本分析时，如果发现是属于预算定额规定的“政策性”亏损，则应该（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","从控制支出着手，把超支额压缩到最低限度",true,{"key":16,"text":17,"correct":18},"B","增加收入，弥补亏损",false,{"key":20,"text":21,"correct":18},"C","采取增收节支措施，防止今后再超支",{"key":23,"text":24,"correct":18},"D","停止生产，等待机会","本题考核的是施工成本分析。 综合成本的分析中，月（季）度成本分析是指施工项目定期的、经常性的中间成本分析，对于具有一次性特点的施工项目来说，有着特别重要的意义。在进行月（季）度成本分析时，发现出现了属于预算定额规定的“政策性”亏损，则应该从控制支出着手，把超支额压缩到最低限度。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]