[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141094":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141094,799,1,"单选题","分部分项工程成本分析“三算”对比分析，是指（ ）的比较。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算成本、目标成本、实际成本",true,{"key":16,"text":17,"correct":18},"B","概算成本、预算成本、决算成本",false,{"key":20,"text":21,"correct":18},"C","月度成本、季度成本、年度成本",{"key":23,"text":24,"correct":18},"D","预算成本、计划成本、目标成本","本题考查的是分部分项工程成本分析的内容。 分部分项工程成本分析的分析方法是：进行预算成本、目标成本和实际成本的“三算”对比，分别计算实际偏差和目标偏差，分析偏差产生的原因，为今后的分部分项工程成本需求节约途径。 综上所述，本题正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]