[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141085":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141085,799,1,"单选题","下列施工成本分析依据中，属于可对已发生，又可对尚未发生或正在发生的经济活动进行核算的是（ ） 2016",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","会计核算",false,{"key":16,"text":17,"correct":14},"B","统计核算",{"key":19,"text":20,"correct":14},"C","成本预测",{"key":22,"text":23,"correct":24},"D","业务核算",true,"本题考查的是施工成本分析的依据。会计和统计核算一般是对已经发生的经济活动进行核算，而业务核算不但可以核算已经完成的项目是否达到原定的目的、取得预期的效果，而且可以对尚未发生或正在发生的经济活动进行核算。参见教材11。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]