[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141083":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141083,799,2,"多选题","进行分部分项工程施工成本分析时，其资料来源包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程合同总价",false,{"key":16,"text":17,"correct":18},"B","实耗人工和材料",true,{"key":20,"text":21,"correct":18},"C","施工预算",{"key":23,"text":24,"correct":14},"D","工程概算",{"key":26,"text":27,"correct":18},"E","实际工程量","BCE","本题主要考查施工成本分析。 进行部分项工程施工成本分析时，分部分项工程成本分析是施工项目成本分析的基础。分析的方法是：进行预算成本、计划成本和实际成本的“三算”对比，分别计算实际偏差和目标偏差，分析偏差产生的原因，为今后的分部分项工程成本寻求节约途径。 分部分项工程成本分析的资料来源是：预算成本来自施工图预算，计划成本来自施工预算，实际成本来自施工任务单的实际工程量、实耗人工和限额领料单的实耗材料。 综上所述，本题正确答案为BCE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]